National
Water Academy
Online Training Activities Database |
ESTIMATE
359 : Preparation of Detailed Project Report
Durartion : 17/1/2011 to 28/1/2011
|
Duration(
Schedule)
:
|
2 Weeks |
Detail Head of Account:
|
|
Coordinated By :
|
Pradeep Kumar, Director (NWA ) | 2701 Major & Medium Irrigation |
| 80.003 Training | ||
| 02 Central Water Commission | ||
| 02.00.20 OAE | ||
|
Estimate Approved By :
|
CE, NWA | |
|
Estimate Prepared For :
|
25 Officers |
Actual No. of Officers
Attended :11
|
|
SrNo.
|
Item
|
Quantity
|
Rate
in Rs.
|
Amount in Rs.
|
ActualExpr.*
|
|
1.
|
Training Material |
30
|
600
|
18000
|
|
|
2.
|
Training Kit |
25
|
300
|
7500
|
|
|
3.
|
Stationary Items |
LS
|
LS
|
1500
|
|
|
4.
|
Tea and Biscuits during Trainig programme |
600
|
10
|
6000
|
|
|
5.
|
Working lunch for trainee Officers |
200
|
75
|
15000
|
|
|
6.
|
Working lunch for Guest Faculty |
20
|
75
|
1500
|
|
|
7.
|
Certificates & Photographs |
26
|
75
|
1950
|
|
|
8.
|
Honorarium to guest Faculty |
28
|
500
|
14000
|
|
|
9.
|
TA/DA for Guest Faculty |
2
|
5000
|
10000
|
|
|
10.
|
Outsourcing of transport for guest faculty |
10
|
800
|
8000
|
|
|
11.
|
Transportation for Field visits |
1
|
5000
|
5000
|
|
|
12.
|
Unforeseen and Miscellanious |
LS
|
LS
|
2550
|
|
|
Total
|
91000
|
0
|
|||
|
Total as per PR Card
|
91000
|
0
|