Name of the Programme : The World Bank Procurement Procedures

Durartion : 13/6/2011 to 17/6/2011

 
Date
Session
SessionTime
SessionType
SessionTopic
Faculty
13/6/2011
I
9:30-11:00 Lecture Contract Law and Arbitration Act of India C M Pandit, Chief Engineer ( NWA ) , NWA
13/6/2011
II
11:30-13:00 Lecture An overview of Hydrology Project -II & Procurement for Externally Aided Projects D S Chaskar, Deputy Director , A&C
13/6/2011
III
14:00-15:30 Lecture The funding mechanism Dalip Kapur, Under Secretary , Dept of Economic Affairs
13/6/2011
IV
16:00-17:30 Lecture The Financial Management Reporting under HP-II D S Chaskar, Deputy Director , A&C
14/6/2011
I
9:30-11:00 Lecture The World Bank loan procedures and documents Dalip Kapur, Under Secretary , Dept of Economic Affairs
14/6/2011
II
11:30-13:00 Lecture Principal of Procurement Arun Kumar Kolsur, Senior Procurement Specialist , World Bank
14/6/2011
III
14:00-15:30 Lecture Guidelines for Procurement Arun Kumar Kolsur, Senior Procurement Specialist , World Bank
14/6/2011
IV
16:00-17:30 Lecture Procurement Process and Standard Bid Documents Arun Kumar Kolsur, Senior Procurement Specialist , World Bank
15/6/2011
I
9:30-11:00 Lecture Procurement of goods/works Arun Kumar Kolsur, Senior Procurement Specialist , World Bank
15/6/2011
II
11:30-13:00 Lecture Procurement of goods/works Arun Kumar Kolsur, Senior Procurement Specialist , World Bank
15/6/2011
III
14:00-15:30 Lecture Procurement of Consultant Services Arun Kumar Kolsur, Senior Procurement Specialist , World Bank
15/6/2011
IV
16:00-17:30 Lecture Procurement of Consultant Services Arun Kumar Kolsur, Senior Procurement Specialist , World Bank
16/6/2011
I
9:30-11:00 Lecture E- Procurement Swayamsiddha Mohanty, Senior Procurement Specialist , The World Bank
16/6/2011
II
11:30-13:00 Lecture Disbursement and Reimbursement Procedures Virendra Singh, Deputy Controller of Aid Audit & Accounts , Ministry of Economic Affairs
16/6/2011
III
14:00-15:30 Lecture Disbursement and Reimbursement Procedures Virendra Singh, Deputy Controller of Aid Audit & Accounts , Ministry of Economic Affairs
16/6/2011
IV
16:00-17:30 FieldVisit Visit to Khadakwasla Dam- NWA
17/6/2011
I
9:30-11:00 Lecture Maharashtra Water Sector Improvement Project - a case study Purnima Desai, Executive Engineer , WRD
17/6/2011
II
11:30-13:00 Lecture Direst Procurements- The Financial Management Reporting under HP II D S Chaskar, Director , A&C
17/6/2011
III
14:00-15:00 Disscussions Discussions & Feedback; Valedictory