Name of the Programme : The World Bank Procurement Procedures
Durartion : 13/6/2011 to 17/6/2011
|
Date
|
Session |
SessionTime
|
SessionType
|
SessionTopic
|
Faculty
|
| 13/6/2011 |
I
|
9:30-11:00 | Lecture | Contract Law and Arbitration Act of India | C M Pandit, Chief Engineer ( NWA ) , NWA |
| 13/6/2011 |
II
|
11:30-13:00 | Lecture | An overview of Hydrology Project -II & Procurement for Externally Aided Projects | D S Chaskar, Deputy Director , A&C |
| 13/6/2011 |
III
|
14:00-15:30 | Lecture | The funding mechanism | Dalip Kapur, Under Secretary , Dept of Economic Affairs |
| 13/6/2011 |
IV
|
16:00-17:30 | Lecture | The Financial Management Reporting under HP-II | D S Chaskar, Deputy Director , A&C |
| 14/6/2011 |
I
|
9:30-11:00 | Lecture | The World Bank loan procedures and documents | Dalip Kapur, Under Secretary , Dept of Economic Affairs |
| 14/6/2011 |
II
|
11:30-13:00 | Lecture | Principal of Procurement | Arun Kumar Kolsur, Senior Procurement Specialist , World Bank |
| 14/6/2011 |
III
|
14:00-15:30 | Lecture | Guidelines for Procurement | Arun Kumar Kolsur, Senior Procurement Specialist , World Bank |
| 14/6/2011 |
IV
|
16:00-17:30 | Lecture | Procurement Process and Standard Bid Documents | Arun Kumar Kolsur, Senior Procurement Specialist , World Bank |
| 15/6/2011 |
I
|
9:30-11:00 | Lecture | Procurement of goods/works | Arun Kumar Kolsur, Senior Procurement Specialist , World Bank |
| 15/6/2011 |
II
|
11:30-13:00 | Lecture | Procurement of goods/works | Arun Kumar Kolsur, Senior Procurement Specialist , World Bank |
| 15/6/2011 |
III
|
14:00-15:30 | Lecture | Procurement of Consultant Services | Arun Kumar Kolsur, Senior Procurement Specialist , World Bank |
| 15/6/2011 |
IV
|
16:00-17:30 | Lecture | Procurement of Consultant Services | Arun Kumar Kolsur, Senior Procurement Specialist , World Bank |
| 16/6/2011 |
I
|
9:30-11:00 | Lecture | E- Procurement | Swayamsiddha Mohanty, Senior Procurement Specialist , The World Bank |
| 16/6/2011 |
II
|
11:30-13:00 | Lecture | Disbursement and Reimbursement Procedures | Virendra Singh, Deputy Controller of Aid Audit & Accounts , Ministry of Economic Affairs |
| 16/6/2011 |
III
|
14:00-15:30 | Lecture | Disbursement and Reimbursement Procedures | Virendra Singh, Deputy Controller of Aid Audit & Accounts , Ministry of Economic Affairs |
| 16/6/2011 |
IV
|
16:00-17:30 | FieldVisit | Visit to Khadakwasla Dam- NWA | |
| 17/6/2011 |
I
|
9:30-11:00 | Lecture | Maharashtra Water Sector Improvement Project - a case study | Purnima Desai, Executive Engineer , WRD |
| 17/6/2011 |
II
|
11:30-13:00 | Lecture | Direst Procurements- The Financial Management Reporting under HP II | D S Chaskar, Director , A&C |
| 17/6/2011 |
III
|
14:00-15:00 | Disscussions | Discussions & Feedback; Valedictory |